Turnkey · 2026-04-02

How to Plan a Turnkey Plastic Cup Production Line

Sequence: cup mix → cavities → former → sheet kg/h → kVA, air, chiller → stacker and crusher → mold freeze. 35–45 day machine lead after drawings.

A cup plant is a chain: resin → sheet → forming → rim/stack/pack → scrap return. If one station is small, the expensive press sits idle. This is the sequence on AMT turnkey projects.

The five gates with numbers

GateWhat you freezeTypical range
1. ProductRim, volume, resin, cases/hourSets cavities and cpm
2. FormerFS / HSS / LS + forming areaSee machine pages (780–850 mm class)
3. Sheetkg/h = cups + skeleton + 10–15%Skeleton often 30–50% of web
4. Utilities380 V, water, 0.6–0.8 MPa airFormer air 2.5–4.0 m³/min on our cup pages
5. DownstreamStack, curl, pack, online crusherSame drawing as the press

Worked layout — one FS-7856 PP cup line

24 cavities × 32 cpm × 60 × 0.85 ≈ 39,000 cups/h. Sheet ~450–500 kg/h. Hall: former + unwind + stacker + online crusher in one row; chiller and compressor in a utility room. After drawing freeze, machine lead time is typically 35–45 days plus mold schedule. Do not pour the air trench after the press arrives.

Do not pour concrete around a missing utility

Mark pits for the former, a 0.6–0.8 MPa air header sized for 2.5–4.0 m³/min plus leak, and a closed chilled-water pair (rolls vs molds) before the press lands. A 35–45 day machine lead is wasted if the trench is cut after uncrating. Spare heaters and a 12-month wear list ship in the same crate as the turnkey — put them on a shelf, not in the office.

Lock CAD on the mold page before steel. Read capacity math first, then quote with hall length and monthly cups.

Fault map — what the line is telling you

SymptomLikely causeFirst check
Press lands; no air trench, no chiller padsCivil work frozen after the crateMark pits and 0.6–0.8 MPa header before the 35–45 day lead ends
Former idle; buying roll stock at a premiumExtruder deferred “until next year” with no width matchPrice sheet line in the same pack even if you stage payment
Compressor in the yard eats filters in a monthDust and heat on an outdoor skidUtility room, not the metal roof
Commissioning overruns with no cpm targetOpen-ended training visitWrite a cycle-time and scrap target in the contract
Spare heaters missing on night shiftWear kit left in the office12-month list on a hall shelf, not in a drawer

RFQ checklist — send this in one email

Fill what you know; blank is better than a guess. Attach it on Get a Quote with photos of resin or flake.

  • Hall length × width and a rough floor sketch (doors, truck, offices)
  • Monthly cups and SKU count; resin mix
  • kVA available, water source, and whether a utility room exists
  • Which stations you already own (extruder, former, stacker, crusher)
  • Mold status: CAD freeze date vs machine 35–45 day lead
  • Language for commissioning and the written cpm / scrap target

Frequently asked questions

How much hall length do I need?

One balanced cup line is often 25–40 m including unwind and stacker. Send a floor sketch; we mark pits and air.

Can I buy the former now and the extruder next year?

Yes, but you will buy roll stock. Price the sheet line in the same pack so widths match.

What spare kit ships with a turnkey?

Heaters, seals, and a 12-month wear list. Hydraulic lines add oil and filter SKUs.

Who trains the operators?

Commissioning crew on site. Budget a written cycle-time target, not an open-ended visit.